Ship Universe Offshore Installation Tool

Subsea Cable Installation Vessel Cost & Weather Downtime Tool

Estimate cable-lay vessel days, burial workload, expected weather downtime, cable-load campaigns, support-vessel costs, specialist spread cost, fuel, port logistics and total marine installation cost. Advanced mode models route segments with different lay rates, burial requirements and weather operability.

Currency selector changes display only. No exchange-rate conversion is performed.
Vessel Days Lay, burial, offshore fixed work, mobilization, loadout, reload and demobilization days
Weather Downtime User-entered segment operability converted into expected standby days and weather cost
Installation Cost Cable vessel, support craft, specialist spread, fuel, port campaigns and fixed project cost

Cable Route & Installation

Simple mode assumes one representative route segment with a single lay rate, burial rate and weather-operability factor.

km
%
m/min
%
m/min
In-line mode uses the slower lay-or-burial process as the production bottleneck.
hours/day
working days
Pull-ins, joints, crossings, testing, route-specific handling or other offshore work.

Weather Operability

Enter the expected percentage of offshore calendar time that is workable for this installation spread. No wave-height, wind-speed or current threshold is assumed by the tool.

%
%
Optional planning contingency applied to calculated weather downtime.

Cable Loadout & Reload Campaigns

tonnes/km
tonnes
Enter 0 to ignore cable-capacity-driven reloads.
days
days
days/reload
days/reload
days
$ /load

Installation Vessel & Marine Spread

$ /day
% normal rate
vessels
$ /vessel/day
$ /offshore day
MT/day
MT/vessel/day
% normal burn
$ /MT
$
$ /installed km
Optional. Leave at 0 to analyze marine installation cost only.

Cable Route Segments

Use different lay rates, burial requirements and weather operability for shallow water, offshore sections, crossings, landfall approaches or other installation zones.

Segment Route km Slack % Lay m/min Burial % Burial m/min Operability % Fixed Offshore Days

Shared Installation Assumptions

hours/day
%

Cable Loadout & Reload Campaigns

tonnes/km
tonnes
days
days
days/reload
days/reload
days
$ /load

Vessel, Spread & Fuel Economics

$ /day
% normal rate
vessels
$ /vessel/day
$ /offshore day
MT/day
MT/vessel/day
% normal burn
$ /MT
$
$ /installed km

Cable Installation & Weather Results

Single-route installation estimate

Enter project data
Enter cable route, installation, weather, vessel and cost assumptions to estimate project duration, standby exposure and marine installation cost.
Planning estimate only. Actual subsea cable installation duration and cost depend on route survey results, geotechnical conditions, water depth, seabed mobility, boulders, crossings, burial depth, trenching tool performance, cable properties, tension limits, bend radius, vessel configuration, cable carousel capacity, landfall method, pull-ins, joints, permits, fisheries restrictions, environmental windows, port availability and project-specific marine procedures. Weather operability should be derived from project-specific metocean data and the actual vessel and equipment limits. This tool does not determine safe operating limits or acceptable weather windows. Day rates, standby rates, fuel treatment and mobilization terms vary by charter and installation contract. Use project-specific engineering, metocean analysis, supplier data and commercial quotations before making contracting or investment decisions.