Emergency Towing Arrangement, Towline Tension, Chock SWL & Tug Bollard Pull Tool
Screen a disabled vessel's towability from environmental resistance through dynamic towline tension, tug bollard-pull requirement, towline and fitting utilization, statutory emergency-towing strength, deployment time and ship-specific emergency-towing readiness. The tool deliberately separates predicted towing force from the approved design load of the emergency towing arrangement.
Regulatory & Vessel Basis
The current tanker ETA requirement and the 1 January 2028 new-ship requirement for non-tankers are different. Emergency towing procedures are a separate requirement and apply much more broadly.
Vessel Geometry & Environmental Tow Resistance
Projected-area drag is a screening model for a disabled vessel. If model-test, sea-trial, CFD, salvage-master or approved towing resistance is available, enter it below as a calibrated override.
Advanced Tow Scenario Register
Compare calm harbor connection, coastal tow, deteriorating weather and worst-plausible cases using the same vessel, tug and fitting capacities.
| Scenario | Speed kn | Wind kn | Wind ° | Current kn | Current ° | Wave add % | DAF |
|---|
Towline, Chock, Strongpoint & Loose Gear
Tug Bollard Pull & Available Tow Force
Deployment & Emergency Towing Booklet Readiness
Optional ETA Upgrade / Towability Budget
This is a procurement and planning section only. It does not convert a deficient arrangement into an approved ETA.