Derecktor to Build Mobile ‘ChargeBarge’ for Vessel-to-Vessel Electric Charging

🔔 Subscribe to ShipUniverse Weekly →

Photon Marine has received the first $1 million MegaBoost award from the NSF Energy Storage Engine in Upstate New York to demonstrate a marine electrification system built around three connected components: a 24-foot production-grade electric workboat, a 40-kW marine DC fast charger and a 32-foot floating battery and charging platform called ChargeBarge. Derecktor Shipyards will fabricate the ChargeBarge in New York. The platform is being developed to carry stored electrical energy to vessels, supporting vessel-to-vessel charging, remote fleet operations, temporary deployments and possible emergency-power use during grid disruptions. The project builds on several seasons of electric-workboat trials with the New York Power Authority and New York State Canal Corporation and is expected to culminate in a fully integrated demonstration in late 2027 or early 2028.

Marine Electrification Infrastructure | September 2026

Instead of Bringing Every Boat to the Charger, Bring the Stored Energy to the Boat

ChargeBarge is intended to move the charging point onto the water. The concept pairs mobile battery storage with marine charging equipment so electric workboats operating away from developed waterfront power can receive energy without a permanent high-power charger at every location.

$1M MegaBoost Award

First award under the NSF Energy Storage Engine's new commercial-scale MegaBoost program.

32 ft ChargeBarge

Floating battery and charging platform to be fabricated in New York by Derecktor Shipyards.

40 kW Marine DC Charger

A separate fast-charging component will be developed and deployed with the demonstration.

300 HP P300 Peak Output

Photon's Gen-7 electric outboard system will power the 24-foot production workboat.

2027-28 Full Demonstration

Integrated operation is targeted for late 2027 or early 2028.

The infrastructure model being tested
Energy Is Loaded

Battery storage on the floating platform is charged where electrical supply is available.

→
ChargeBarge Is Repositioned

Stored electricity can be moved toward a work area instead of installing permanent high-power infrastructure at every waterfront location.

→
Energy Transfers to the Vessel

Electric workboats can receive power at or near their operating location through vessel-to-vessel charging.

Remote Fleets Bring stored energy closer to vessels operating away from developed charging sites.
Temporary Operations Position charging capacity for projects or events that do not justify permanent infrastructure.
Vessel-to-Vessel Transfer stored electrical energy directly from the floating platform to an electric vessel.
Emergency Power The project will evaluate potential energy-storage uses during grid disruptions.
Two specifications have not yet been publicly disclosed: the ChargeBarge's total battery-storage capacity in kWh and its maximum vessel-transfer power. Those figures will ultimately determine how many boats it can recharge before returning to an energy source and how quickly those transfers can occur.

From a Test Boat to a Complete Energy System

The MegaBoost project adds charging and mobile energy storage to a workboat program that has already spent several seasons testing day-to-day Canal Corporation jobs.

System Element Configuration Role Previous Experience MegaBoost Phase
Electric Workboat Field Tested 24-foot production-grade workboat using Photon Marine's Gen-7 P300 electric propulsion system. Perform commercial and government workboat missions while producing real duty-cycle and energy-consumption data. Earlier Photon-powered test boats were used for buoy retrieval, dredge-pipe towing, crew transport and debris removal on the New York State Canal System. Move from leased pilot hardware toward a production-representative vessel configuration.
Marine DC Charger 40 kW Dedicated 40-kW DC charging infrastructure for electric commercial, government and recreational vessels. Provide a faster fixed charging point and generate real utilization data. Earlier Canal testing largely depended on existing electrical connections and overnight charging. Develop and deploy purpose-built marine DC fast-charging capability.
ChargeBarge New Build 32-foot floating platform carrying battery energy storage and high-power charging equipment. Move stored electrical energy toward the operating vessel rather than requiring fixed charging at every location. No ChargeBarge operated in the earlier NYPA pilot. Fabrication by Derecktor Shipyards followed by vessel-to-vessel and remote-fleet testing.
Data Layer Fleet Analytics Vessel performance, battery state of charge, battery health, duty cycle and charging records. Determine how much energy real missions consume and where charging infrastructure is actually required. Prior trials already generated operational experience and battery-monitoring data. Add charging utilization, vessel-to-vessel energy transfer and potential grid applications.
Deployment Playbook Commercialization Fleet-electrification guidance based on the completed demonstration. Give other operators a repeatable framework for assessing electric vessels, chargers and energy storage. Earlier trials were primarily designed to establish whether electric workboats could perform Canal Corporation missions. Translate the demonstration into a model intended for other U.S. commercial fleets.
200+ miles Long-Distance Canal Trial

The earlier test boat was operated more than 200 miles from Buffalo to Syracuse during 2025 Erie Canal bicentennial activities.

~50 miles Longest Reported Leg

One roughly ten-hour leg was completed at about four to four-and-a-half knots, with approximately 30% battery charge remaining.

5:30 a.m. The Charging Problem Was Practical

Canal crews worried about arriving for work to find a vessel incompletely charged because an electric boat cannot simply be refueled in minutes like the gasoline workboat beside it.

Derecktor Brings Existing Hybrid-Vessel Experience

Derecktor's Mamaroneck yard remains its new-construction base. The company has previously delivered multiple hybrid commercial vessels and describes itself as an early U.S. builder of commercial hybrid craft, giving the ChargeBarge project a shipyard partner with prior experience integrating marine electrical and energy systems.

Mobile Marine Charging Mission Planner

Model how a battery-equipped charging platform could support a remote electric workboat fleet. Because Photon has not disclosed ChargeBarge battery capacity or transfer power, those fields are intentionally editable assumptions.

Important: The default 500-kWh platform capacity below is illustrative and is not a published ChargeBarge specification. Change it as needed when actual system specifications become available.
Deliverable Energy 391 kWh
Full Vessel Sessions 7
Time Per Vessel 85 min
Platform Recharge 5.0 hr

Mission Energy Requirement

Available Energy
391 kWh
Fleet Requirement
300 kWh
Simplified planning model only. Actual charging performance will depend on battery chemistry, state of charge, thermal limits, cable and connector ratings, charging curves, conversion losses, weather, vessel motion, marine electrical standards, platform hotel loads and safety-management requirements.