8 Shipyard Scheduling Mistakes That Make Small Retrofits Expensive

Small retrofits become expensive when owners treat them like minor add-ons instead of drydock projects competing for the same scarce slot, engineering time, approvals, maker attendance, and yard labor as major work. The current market evidence points in that direction. DNV says drydocking is the largest maintenance cost for shipping companies and that drydock and retrofit projects need professional tender management with integrated work-item collection, quotation handling, and yard-supplier comparison. LR says owners need to plan retrofit timing around budget, capital requirements, and drydock availability to avoid unnecessary cost and penalties, and that detailed planning and risk management are needed to minimise time in drydock. BIMCO’s Ship PI framework also makes the trap clear: agreed drydocking budget and duration are defined before docking starts, while actual drydocking cost includes additional work not planned before docking and any extra duration approved after docking starts.
| # | Scheduling mistake | Appearance in practice | Growing Expense | Where the cost shows up | Owners may miss | Best correction before docking | Priority |
|---|---|---|---|---|---|---|---|
| 1️⃣ |
Booking the yard slot before freezing the real retrofit scope
The calendar is fixed but the work pack is still moving
|
The owner locks in a class slot early, then keeps adding or redefining small retrofit tasks as the docking approaches. | Late-added work competes with already-planned steel, blasting, class items, and vendor windows, which raises labour inefficiency and extension risk. | Variation orders, extra yard days, and higher supervision load. | A “small” retrofit added late can still disrupt the whole docking sequence because access and sequencing matter more than equipment size. | Freeze the retrofit package early enough that yard sequencing, drawings, and maker attendance can be built around a stable list. | High |
| 2️⃣ |
Waiting too long to reserve the slot for work that needs scarce yard capability
Not every yard can absorb even a modest retrofit cleanly
|
The owner assumes the work is minor, so any class slot will do, then discovers the retrofit needs specific lifting, steel, piping, electrical, or commissioning capability. | Limited-capability yards compensate with slower execution, subcontract layers, or awkward resequencing, which pushes up total cost. | Higher unit labour cost, longer docking, and more claims over delays or incomplete commissioning. | Availability is not the same as suitability. A yard with a free slot may still be the wrong yard for the exact retrofit package. | Match the retrofit type to yard capability first, then lock the slot, not the other way around. | High |
| 3️⃣ |
Treating the retrofit as separate from class and repair sequencing
Parallel work on paper becomes serial work in dock
|
The retrofit is tendered as a standalone package without fully mapping when the same space, structure, or systems are already needed for class renewal items. | Work gets repeated, access is blocked, staging is duplicated, and teams wait on each other instead of progressing in parallel. | Crane time, scaffolding, tank access, hot work windows, and duplicated attendance. | The owner thinks the retrofit is a bolt-on package when it is really competing for the same access windows as survey and repair work. | Build one integrated docking sequence covering class items, repairs, and retrofit tasks together. | Core |
| 4️⃣ |
Starting procurement too late for “small” items that are actually long lead
Minor equipment packages often fail on delivery timing, not complexity
|
Sensors, valves, control panels, cabling, specialist brackets, maker kits, or software licenses are ordered after the slot is already close. | The ship reaches dock before the full package is physically ready, forcing partial completion, temporary solutions, or expensive express logistics. | Air freight, idle labour, resequencing, incomplete commissioning, and return visits. | Owners often price only the item itself, not the cost of one missing item holding up a whole package. | Run a lead-time map for every retrofit component, not just the headline equipment. | High |
| 5️⃣ |
Leaving maker attendance and commissioning windows too late
The hardware arrives but the specialist does not
|
The yard work finishes, but OEM or approved technician attendance is not aligned with installation completion, testing, or class witness needs. | Completed work sits idle waiting for sign-off, software loading, calibration, or commissioning. | Extended docking, standby cost, and sometimes sailing with unfinished performance or return attendance later. | The maker’s calendar can be as critical as the yard slot, especially for controls, electronics, and certified systems. | Book attendance against the planned critical path, with buffer for slippage on preceding tasks. | Core |
| 6️⃣ |
Underestimating approvals, drawings, and class-review time
A small retrofit can still have a long paper trail
|
The owner assumes the package is too minor to need extensive engineering or approval work, then loses time on late drawing revisions and unanswered comments. | Installation cannot proceed cleanly if the design package is incomplete, unclear, or still being revised close to docking. | Engineering rework, site clarification, delayed fabrication, and postponed installation start. | Paper delay often becomes physical delay because fabrication, cable routing, supports, and testing all depend on approved information. | Push the approval path early enough that the yard receives a buildable package, not an evolving concept. | High |
| 7️⃣ |
Skipping early measurement and prefabrication opportunities
Too much onboard cutting and fitting is left for dock time
|
Supports, spool pieces, cabling runs, or foundations that could have been measured and prefabricated earlier are deferred until the ship is in dock. | Every extra hour of dockside fit-up consumes expensive yard time and increases the risk of discovering new clashes after the clock starts. | Steelwork hours, pipefitting, cable installation, and hot work duration. | Owners focus on buying equipment but forget that fabrication and fit-up are often the real time drivers. | Use pre-docking measurement and prefabrication to shift as much work as possible off the critical dock window. | Money |
| 8️⃣ |
Approving “just one more item” after the dock has already started
Late additions are the classic small-retrofit cost multiplier
|
Once the ship is already in dock, the team decides to add adjacent improvements, repairs, or small modifications because access appears convenient. | According to BIMCO Ship PI logic, actual drydocking cost includes additional work not planned before docking, and extra duration agreed after start moves the project away from the original plan. | Budget blowout, extension claims, procurement chaos, and fatigue in yard coordination. | Late additions often look efficient in isolation but are expensive because they disrupt a schedule already under compression. | Use a strict late-addition gate and approve extra scope only when the commercial value clearly beats the delay risk. | High |
This is a directional owner tool. It does not replace yard tendering, class review, or detailed retrofit planning. It helps show whether scheduling mistakes are likely to inflate the cost of a small package once the dock clock starts.
We welcome your feedback, suggestions, corrections, and ideas for enhancements. Please click here to get in touch.