APM Terminals Maasvlakte II and the Port of Rotterdam Authority announced plans on November 24, 2026, for another phase of container-terminal expansion at Prinses Amaliahaven in Rotterdam. The development would add approximately 1.4 million TEU of annual handling capacity, 25 hectares of terminal land and 711 metres of quay wall. Supporting works include 428 metres of landside crane rail and dredging approximately 1.3 million cubic metres of sand. An investment decision by the Port Authority's shareholders is expected in February 2027, with construction currently scheduled from October 2027 through January 2030. The expansion remains subject to further technical development, investment approval and procurement.
Rotterdam Adds 1.4 Million TEU of Planned Capacity While Transshipment Falls 20%
The new Maasvlakte II development extends one of Europe's most automated container terminals. But the investment comes against almost flat total container volumes, competing terminal expansions and a growing contest to secure major shipping-line networks.
TEU per year, projected
Additional quay wall
Approximately 62 acres
Works scheduled to end January
The November 24 project description separates maritime civil works from the terminal operator's equipment and operational development.
| Project Element | Announced Scope | Function |
|---|---|---|
| Terminal expansion | 25 hectares | Additional operational land for container handling and related facilities. |
| Quay extension | 711 metres | More waterfront infrastructure for deep-sea and other container vessel operations. |
| Crane rail extension | 428 metres | Expansion of landside crane infrastructure; distinct from the full quay-wall length. |
| Dredging | Approximately 1.3M m³ | Marine works necessary for the new infrastructure. |
| Annual throughput capacity | +1.4M TEU | Estimated additional handling capability once the development is complete. |
| Maritime infrastructure | Port Authority responsibility | Site preparation, quay wall and associated port works. |
| Terminal development | APM Terminals responsibility | Operational development and integration with the existing automated terminal. |
Rotterdam's official January–September 2026 figures provide a more revealing picture than overall port tonnage.
Growth in the first nine months of 2026 compared with the previous year.
Container transshipment declined as capacity constraints and network changes shifted cargo elsewhere.
Traffic moving to and from inland markets increased, including growth in full-container imports.
The Port Authority specifically identified long-standing restrictions at Rotterdam's deep-sea terminals as one reason transshipment cargo moved to other ports, freeing capacity for hinterland flows. Full-container imports increased 8.9%, while full-container exports grew 1% during the first nine months.
Additional berth and yard capacity could allow Rotterdam to compete for transshipment volumes previously diverted by terminal constraints.
If additional cargo fails to materialise, new infrastructure could increase competitive pressure on terminal utilisation and handling charges.
| Target Date | Milestone | Current Status |
|---|---|---|
| November 24, 2026 | Next expansion phase announced | Confirmed announcement |
| January 2027 | Contractor pre-selection published through TenderNed | Planned procurement step |
| February 2027 | Port Authority shareholder investment decision | Expected, not yet approved |
| March 2027 | Start of quay-wall tender award phase | Scheduled procurement step, not an awarded contract |
| October 2027 | Construction commencement | Planned |
| January 2030 | Scheduled completion of construction works | Target date; commercial ramp-up not separately specified |
Different announcements describe phases and configurations of the same evolving terminal development.
| Announcement | Published Scope | Interpretation |
|---|---|---|
| March 2023 | Approximately 47.5 hectares, 1,000m of quay and 2M TEU additional capacity | Earlier major development agreement |
| August 2026 | 2,000m total deep-sea quay and expected 5.4M TEU annual terminal capacity | Published post-expansion terminal configuration |
| November 2026 | 25 hectares, 711m quay extension and 1.4M TEU additional annual capacity | Next announced development phase with its own approval and construction schedule |
The first part of the wider terminal expansion has recently entered operation. The November announcement describes the next phase while the existing facility continues working.
Hapag-Lloyd completed its acquisition of a minority stake in Maasvlakte II through Hanseatic Global Terminals following antitrust clearance.
The Maersk-affiliated operator retains operational control. Maasvlakte II is an important European hub for the Gemini Cooperation.
The ownership structure reinforces a significant shift in container-port economics: large liner operators are securing long-term infrastructure access rather than relying exclusively on third-party handling contracts. Terminal capacity can become part of an integrated network strategy covering schedule reliability, vessel exchanges, cargo connectivity and equipment flows.
Another major automated Maasvlakte terminal is advancing its own investment programme before 2030.
| RWG Development | Published Scope | Commercial Relevance |
|---|---|---|
| Fourth deep-sea berth | Targeted before 2030 | More berth capacity for the largest container vessels |
| Quay cranes | 5 additional | Increased ship-to-shore handling capacity |
| Automated stacking cranes | 22 additional | Greater automated yard capacity across 11 new storage modules |
| Automated guided vehicles | 24 additional | Expanded horizontal container transport |
| Latest investment phase | Approximately €500M | Capital commitment by RWG and its financing partners |
| Expected total capacity | Approximately 5M TEU | Post-expansion terminal-level target |
RWG is backed by shareholders including DP World, CMA CGM, ONE and HMM. The expansion creates another large automated platform competing for carrier networks, transshipment volumes and inland cargo flows within Rotterdam itself.
Official full-year 2025 container volumes. These are port-wide actual throughput figures, not terminal design capacities.
| Port | 2025 Throughput | Competitive Context |
|---|---|---|
| Rotterdam | 14.2M TEU | Europe's leading container port, investing in further automated terminal capacity. |
| Antwerp-Bruges | Approximately 13.6M TEU | Major competing gateway with its own extra-container-capacity programme. |
| Hamburg | 8.3M TEU | Germany's largest seaport, with established rail connections and feeder networks. |
Rotterdam's proposed 1.4M-TEU capacity addition is large relative to annual throughput in the North European port range. But additional terminal space alone will not determine market share. Carrier alliances, berth windows, inland connections, reliability and total handling costs will shape where cargo is routed.
APM's existing terminal uses electrified equipment, automated guided vehicles and remotely operated quay cranes. Expanding the waterfront requires corresponding capacity across the terminal system.
Quay availability is useful only when crane deployment, vessel sequencing and call exchanges can be handled reliably.
Yard cranes and horizontal transport must prevent ship-side improvements from becoming landside congestion.
Expanded rail and inland-waterway connections are essential for moving additional volumes beyond the terminal.
One operational warning is already visible. APM temporarily reduced available rail capacity by approximately 40% from July 2026 through an indicative June 2027 end date to accommodate reconfiguration and testing associated with its ongoing expansion programme. That restriction predates the newly announced 2027–2030 construction phase.
| Measure | Positive Outcome | Outstanding Question |
|---|---|---|
| Capacity utilisation | Additional cargo volumes absorbed without significant idle infrastructure | How quickly can new capacity be filled? |
| Transshipment recovery | Previously diverted traffic returns to Rotterdam | How much lost cargo is recoverable? |
| Vessel productivity | More reliable berth access and faster cargo exchanges | What verified turnaround improvement is achievable? |
| Hinterland performance | Higher throughput without growing rail, barge or truck delays | Will inland transport capacity expand at the same pace? |
| Investment economics | Sustained revenue and asset productivity relative to the final project cost | What will the approved capital budget and customer commitments show? |
Rotterdam's proposed 1.4 million-TEU addition is another substantial step in the Maasvlakte II build-out, but its commercial significance extends beyond new quay length and automated equipment. With transshipment volumes declining and competing terminals expanding, the investment will be judged by the cargo it attracts, the reliability it delivers and the efficiency of its hinterland connections. The February 2027 investment decision and subsequent contracting process will determine whether the latest phase proceeds on the announced timetable.