The Port of Long Beach placed two major infrastructure authorizations on its November 23, 2026, Harbor Commission agenda. Item HD-26-577 requested authority for a $23.138 million ninth change order on the Berth G234 Wharf and Pier G South Slip Fill project, which is expanding the container terminal operated by International Transportation Service. A separate item, HD-26-561, sought a $25.5 million spending authorization and an amendment to the port's memorandum of understanding with the Department of the Army to advance construction-phase activities for the Long Beach Deep Draft Navigation Improvements project. The same agenda also included a proposed $970,000 net eighth change order for the Pier G work. The proposals concern separate infrastructure programs; the agenda itself does not establish final approvals, executed amendments or a construction budget overrun.
Long Beach Weighs $23.1 Million Wharf Change Order as Deep-Draft Costs Climb
Two separate construction authorizations expose different financial questions: who ultimately pays for Pier G modifications, and how a more expensive harbor-deepening program moves into construction.
Proposed November 23 authorization
Separate Army memorandum amendment
FY2025 financial-report figure
USACE 2026 validation estimate
The November 23 agenda requested executive authority. It does not, by itself, document final voting results or executed contracts.
| Agenda Item | Amount | Proposed Action | Project |
|---|---|---|---|
| HD-26-551 | $970,000 net | Authorize Change Order No. 8, comprising $4.652 million of additions and $3.682 million of deductions. | Pier G wharf and slip fill |
| HD-26-577 | $23,138,000 | Authorize execution of Change Order No. 9. | Pier G wharf and slip fill |
| HD-26-561 | $25,500,000 | Authorize Amendment No. 1 to the Department of the Army memorandum and associated spending. | Deep-Draft Navigation Improvements |
The City of Long Beach's audited FY2025 financial statements identify an availability-payment arrangement with International Transportation Service, LLC (ITS).
| Financial Provision | Documented Arrangement |
|---|---|
| Estimated Project Cost | $300 million in the FY2025 audited statements. |
| ITS Responsibility | Design, construction and financing of the estimated project cost. |
| Conditional Harbor Exposure | The Harbor Department agrees to fund costs above the $300 million estimate, up to $50 million if needed. |
| Construction-Period Payments | Monthly contributions equivalent to 5% annual simple interest on approved reimbursable costs. |
| Repayment Structure | After substantial completion, approved reimbursable costs are repaid through monthly rent credits or cash payments at the Harbor Department's option, with a 5% simple-interest provision. |
| Timing | Substantial completion anticipated in December 2028; repayments could extend through the agreement's August 2051 expiration. |
Cumulative project expenses reported in the FY2025 audit. This is a historical balance, not the current total construction cost.
Applied to approved reimbursable costs under the arrangement, with monthly contributions during construction and a post-completion repayment mechanism.
A separate July 2025 financing announcement described the Slip Fill development as a $365 million project supported in part by $424 million of new credit facilities. Those transaction figures should not be treated as directly comparable to the audit's $300 million estimate: the published descriptions do not reconcile their respective scopes, financing uses and measurement dates.
Change Order No. 8 has a documented net composition: $4.652 million in additive items offset by $3.682 million in deductions. The agenda identifies the amount of Change Order No. 9 but does not provide an independently verified breakdown of its underlying construction scope.
The ninth change order's stated amount equals approximately 7.7% of the historical audited project estimate. This is a scale comparison, not a calculated overrun.
The accessible agenda does not determine whether the change affects ITS financing, Harbor reimbursements or another cost allocation.
December 2028 remains the completion target cited in the audited financial report. A revised date attributable to the ninth change order has not been established.
The Army Corps' 2026 validation listing identifies a substantial revision to the navigation project's estimated first cost, separate from Pier G.
The previous $175.787 million authorized-cost figure restated to fiscal-year 2026 price levels.
An increase of $66.503 million, or approximately 35.1%, on a consistent FY2026 price basis.
The navigation program addresses constraints in the Approach Channel, Main Channel, West Basin and Pier J approaches, including deeper and wider navigation areas for large commercial ships. The proposed November 23 memorandum amendment would allow the port to advance construction-phase work with the Army, subject to authorization and agreement terms.
| Decision Point | What Still Needs Confirmation | Commercial Consequence |
|---|---|---|
| Pier G Change Order | Detailed scope, price justification, funding allocation and any schedule adjustment. | Determines the actual effect on construction economics and Harbor reimbursement exposure. |
| Availability Payments | Updated approved reimbursable balance and projected post-completion payment schedule. | Clarifies the longer-term financial obligation beyond construction. |
| Army Memorandum | Specific work packages, timing, funding credits and responsibility under Amendment No. 1. | Shows how construction is being advanced and funded. |
| Board Disposition | Recorded November 23 votes, final signed change orders and executed memorandum. | Separates proposed authority from binding project commitments. |
Long Beach's November 23 agenda places two different infrastructure financing decisions under scrutiny. The $23.138 million Pier G change order raises an unresolved question about cost allocation within a long-term reimbursement arrangement, while the deep-draft program is moving toward construction under a substantially higher revised estimate. The financial effects will depend on the final approvals, contract details and updated project budgets—not the agenda amounts alone.