Pakistan's Public Procurement Regulatory Authority published a final bid evaluation on November 20, 2026, showing that only one construction bid was received for infrastructure works at Gwadar Port Authority's proposed 100-acre off-dock terminal. Saleh Techno Enterprises, identified as a sole proprietorship, was the sole bidder listed following the November 10 tender closing. The project is located along the Coastal Highway near New Gwadar International Airport and includes boundary construction, roads, an office, warehouse foundation works and partial land preparation. The bidding documents specify a 230-day construction schedule and contain a reference bill of quantities totaling PKR 237.2 million. No signed construction contract or final award price is established by the published evaluation.
Gwadar's 100-Acre Expansion Draws One Bid — And the Tender Reveals a Smaller First Phase
Pakistan's procurement records expose a limited construction field, an earlier tender attempt and a civil-works package that stops well short of delivering a fully operational cargo terminal.
Saleh Techno Enterprises listed as lowest bidder
Land covered by the proposed boundary wall
Reference cost, not an awarded contract value
Specified delivery period in tender documents
One Bid, One Named Firm — But No Confirmed Contract Price
The November 20 final evaluation identifies the bidder without establishing a signed construction agreement.
| Procurement Detail | Official Record | Interpretation |
|---|---|---|
| Tender Reference | GPA/P&D/2026/05 PPRA TS0000016688E |
Civil infrastructure works at the planned off-dock terminal |
| Tender Advertised | October 23, 2026 | Public construction competition |
| Bid Closing | November 10, 2026 | One bid received |
| Final Evaluation Published | November 20, 2026 | Final evaluation notice, not a published contract agreement |
| Named Bidder | Saleh Techno Enterprises Sole proprietorship |
Listed as lowest bidder in PPRA record |
| Winning Price / Award | Not established by the evaluation notice | Published BOQ rates must not be treated as the firm's actual offer |
The Project Was Already Tendered in 2025
A previous Gwadar Port Authority bidding document shows that the same named infrastructure project had been offered to contractors a year earlier.
| Procurement Stage | Published Terms | What Is Established |
|---|---|---|
| November 2025 Tender | November 7 closing date; 12-month completion period | GPA previously sought contractors for off-dock infrastructure works |
| October–November 2026 Tender | November 10 closing date; 230-day delivery schedule | A subsequent procurement with a shorter specified period |
| November 20 Evaluation | One bid received | Only one participant is identified in the published 2026 evaluation |
100 Acres of Land. Only 25 Acres Specified for Filling and Leveling.
The 161-page bidding document separates the project's overall land footprint from the actual civil works being procured.
Approximately 40.5 hectares. The boundary wall is intended to secure the planned off-dock terminal footprint.
Approximately 10.1 hectares identified for sand filling and leveling under this package.
| Work Package | Included in Tender | Commercial Significance |
|---|---|---|
| Boundary Wall | Enclosure of 100-acre property | Site security and perimeter infrastructure |
| Land Preparation | Sand filling and leveling of 25 acres | Initial ground preparation rather than full-site development |
| Internal Roads | Road construction and associated earthworks | Internal vehicle circulation |
| Administrative Office | Office-building construction | Administrative facilities for the project |
| Warehouse Base | Civil foundation/base works | Does not itself establish completion of a working warehouse |
PKR 237.2 Million Is a Reference Estimate, Not the Winning Bid
The published bill of quantities contains a grand total of PKR 237,207,302 across the specified works.
Value at the reference rates listed in the construction document.
Financial security specified in the tender, approximately 2% of the BOQ reference total.
Performance guarantee specified in the bidding document, with 5% retention provisions.
The Tender Conditions Also Deserve Attention
The procurement was not an unrestricted open call for every civil-works contractor.
| Bid Requirement | 2026 Procurement Terms |
|---|---|
| Contractor Registration | Pakistan Engineering Council category C-3 with specified specialized codes |
| Technical Qualification | Minimum 70 marks out of 100; relevant completed construction projects and engineering personnel assessed |
| Joint Ventures | Joint ventures, consortiums and associations marked as not permitted |
| Selection Method | Single Stage–Two Envelope; Least Cost Based Selection |
These requirements define the eligible bidding field. Their effect on participation cannot be determined from the one-bid result alone; the published evaluation does not explain why other firms did not submit offers.
A Separate Consultancy Tender Follows the Evaluation
Gwadar Port Authority advertised another procurement one day after releasing the construction evaluation.
Final evaluation published for GPA/P&D/2026/05, identifying one construction bidder.
Separate tender GPA/P&D/2026/07 advertised for consultancy services related to the infrastructure works. Scheduled closing: November 26 at 09:00 Pakistan time.
The Real Gap Is Between Civil Infrastructure and Cargo Capacity
The off-dock project adds a prospective land-side logistics facility, not new waterfront capacity under this tender.
| Development Question | What Is Documented | What Remains Unestablished |
|---|---|---|
| Land Availability | GPA lists acquisition of 100 acres for the off-dock terminal among completed FY2022–23 projects | Full readiness of the land for commercial cargo operations |
| Marine Interface | Gwadar already has three multipurpose berths and a 602-meter main quay | Dedicated arrangements linking the inland terminal to vessel and customs operations |
| Terminal Equipment | Initial civil works, office, roads and warehouse base | Future handling equipment, operating systems and completed storage facilities |
| Commercial Capacity | 100-acre planned footprint, with 25 acres specifically designated for filling and leveling | Operational throughput, cargo mix, customers and commissioning date |
Gwadar's off-dock terminal has progressed through land acquisition and successive procurement exercises, but its latest civil-works tender attracted only one bidder. The published scope is principally enabling infrastructure rather than a finished cargo facility. With a separate consultancy competition underway, the next substantive milestones are a confirmed construction award, mobilization of works and disclosure of the additional investments needed to turn the site into operating terminal capacity.