Delfin LNG LLC has requested a sixth extension of the construction deadline for the onshore natural gas facilities supporting its planned floating LNG export terminal off Cameron Parish, Louisiana. The application was filed with the Federal Energy Regulatory Commission on October 30, 2026, and published in the Federal Register on November 16 under Docket CP15-490-005. Delfin is asking to move the deadline for its metering, compression and piping facilities from September 28, 2027, to September 28, 2030. The company reached a reported $5 billion final investment decision for its first floating LNG unit on June 3 and expects the vessel to arrive at the offshore port in 2030. Its separate October 1 filing with the Department of Energy projects first commercial operations in the first half of 2031. FERC has not ruled on the new extension request. Comments and interventions are due November 25, 2026.
The 13-Year Construction Clock Behind Delfin's $5 Billion Investment
Five approved deadline extensions, one new three-year request and several separate federal authorizations now define the path to the first commercial LNG exports.
How the Deadline Changed
A $5 Billion Decision Does Not Complete the Entire Gas Supply Chain
Delfin's investment decision covers its first floating LNG development phase. The facilities authorized under FERC's onshore certificate are separate infrastructure that must connect the U.S. gas network to the offshore deepwater port.
June 3 final investment decision, backed by investors including Global Infrastructure Partners, Mitsui O.S.K. Lines, Vitol and Diameter Capital Partners. Planned first-unit capacity is 4.4 million tonnes per year.
Samsung's publicly disclosed construction contract for FLNG Unit 1. This is a component of the wider development, not an additional $2.9 billion to be automatically added to the $5 billion project figure.
Six Milestones That Must Not Be Confused
Construction authorizations, project investment, vessel arrival, commissioning and commercial cargo delivery represent different events.
| Milestone | Date / Status | What the Record Establishes | What It Does Not Establish |
|---|---|---|---|
| FERC Onshore Certificate | September 28, 2017 | Authorization to construct and operate specific Cameron Parish metering, compression and piping facilities. | It did not authorize the offshore port or prove that onshore construction was finished. |
| Fifth Deadline Extension | Approved October 4, 2023 | FERC granted a four-year extension, establishing September 28, 2027 as the current deadline. | It did not guarantee that the work would be completed by 2027. |
| Offshore Deepwater Port License | Issued March 21, 2025 | MARAD authorized the offshore deepwater port under the Deepwater Port Act. | It did not replace FERC's land-side construction deadlines or DOE export conditions. |
| First FLNG Investment Decision | June 3, 2026 | Delfin announced a $5 billion FID for Unit 1 and executed construction arrangements. | It is not proof that $5 billion has already been paid out or that commercial operation has begun. |
| Sixth FERC Extension | September 28, 2030 requested | Delfin seeks another three years for its onshore gas delivery infrastructure, citing the vessel's anticipated 2030 arrival. | The extension has not yet been granted and is subject to the pending proceeding. |
| First FLNG Commercial Operations | First half of 2031, projected | Delfin's October 1 report to DOE states this expected operating window for Unit 1. | This is a company projection, not proof of commissioning, first LNG production or a completed cargo. |
| DOE Export Commencement Condition | June 1, 2031 | The current deadline for commencing authorized non-FTA exports, following DOE's 2025 decisions. | The date is a regulatory condition, not a guaranteed first-delivery date. |
| Note | Some project milestones may occur earlier than the final regulatory deadlines. The 2030 arrival of the first offshore vessel and first-half 2031 commercial operations are separate company expectations. | ||
Four Different Regulatory Responsibilities
Approves specified metering, compression and piping facilities and considers construction-deadline extensions.
Licenses the planned floating LNG deepwater port together with the Coast Guard's role in the licensing process.
Maintains export authorizations and the commercial export-commencement conditions.
Oversees applicable pipeline-safety obligations, including a separate corrective-action case concerning Delfin's existing gas pipeline.
The Other Pipeline Issue Behind Delfin's 2031 Timeline
Federal safety records, a DOE progress report and an LNG buyer's securities filing expose infrastructure and commercial milestones beyond the latest FERC request.
A February Pipeline Failure Remains Part of the Infrastructure Picture
Delfin's existing offshore gas pipeline was being inspected ahead of future service when it ruptured near Johnson Bayou. The accident is documented separately from FERC's pending construction-deadline application.
Approximate natural gas release reported by PHMSA, followed by a fire.
One person was injured during the pipeline failure, according to the agency.
Corrective-action case status in PHMSA's data snapshot dated November 3, 2026.
The February 6 order prohibits operating the affected pipeline segment until permitted by PHMSA's regional director. Required measures include independent assessment, a root-cause investigation, repairs and an approved restart plan. The agency's early finding suggested that an inspection pig may have encountered a closed valve, but it explicitly described its investigation findings as preliminary.
Two Different Sets of Pipeline Facilities
Approximately two miles of metering, piping and compression facilities, including 120,000 horsepower of planned compression. The requested in-service deadline is September 28, 2030.
An approximately 30-mile, 42-inch pipeline extending from West Cameron Block 167 toward Johnson Bayou. PHMSA says it had been out of service since 2012 before the February 2026 inspection-related rupture.
The Production Date and Commercial Delivery Date Are Different
Primary corporate, DOE and SEC filings provide a more detailed sequence than the company's investment announcement alone.
Seven Questions That Determine Whether the Schedule Holds
The following matrix separates documented obligations from the areas where construction, shipbuilding and commercial stakeholders still need specific dates or confirmations.
| Project Dependency | Confirmed Record | Unresolved Milestone | Why Shipping & Energy Stakeholders Care |
|---|---|---|---|
| Sixth FERC Extension | Three additional years requested for Cameron Parish onshore metering, compression and piping facilities. | FERC approval, conditions and revised construction milestone schedule. | Contractors and equipment suppliers need a workable project delivery schedule; the new deadline is not yet approved. |
| Existing Gas Pipeline | PHMSA issued a corrective-action order after the February rupture. Its enforcement database listed the case as open at the November 3 update. | Verified completion of required tests, repairs and approved restart authorization. | Gas-delivery readiness remains a separate requirement from constructing the floating liquefaction vessel. |
| FLNG Unit 1 Construction | Samsung Heavy Industries announced a construction contract of approximately $2.9 billion; Delfin reached its $5 billion first-phase FID. | Verified hull and topside construction progress, factory acceptance testing, delivery and offshore installation. | Schedule reliability influences marine installation resources, offshore support demand and future LNG carrier availability. |
| Gas Supply Agreements | In its October 1 DOE report, Delfin stated that it had not yet entered into long-term natural gas supply contracts. | Feedgas contracting, transportation arrangements and physical commissioning supply. | Long-term LNG sale agreements do not themselves prove that all required feedgas arrangements are complete. |
| LNG Offtake & Buyers | Delfin identifies Vitol, Centrica, Gunvor and Expand among its commercial counterparties. Expand's SEC filing describes 1.15 million tonnes annually with deliveries expected in 2031. | Shipment nomination windows, first commercial cargo, contractual startup conditions and final delivery arrangements. | LNG carriers and buyers need actual lifting schedules before treating potential 2030 capacity as operating supply. |
| Export Authorization Timing | DOE's current commercial non-FTA export commencement deadline is June 1, 2031. | A precise startup date and confirmation that it fits the export authorization's conditions. | The first-half 2031 projection spans January through June, while the existing deadline occurs June 1. That is a scheduling issue to clarify, not evidence of an existing violation. |
| FLNG Units 2 and 3 | Delfin is separately advancing additional units and has discussed potential investment in Unit 2 with MidOcean Energy. | Separate final investment decisions, construction awards, financing and commercial commissioning. | Potential 13.2 million tonnes per year of total project capacity should not be counted as three operating units or three completed investment decisions. |
| Note | A reported risk is not a confirmed delay or cost overrun. The records establish separate approval and execution milestones, but do not disclose a verified consolidated critical path or damages arising from any hypothetical missed startup date. | ||
Comments and motions to intervene in FERC Docket CP15-490-005 are due by 5:00 p.m. Eastern. FERC must still decide whether Delfin has shown good cause for the extension.
Look for a FERC order, pipeline restart authorization, updated Samsung delivery milestones, actual commissioning plans and confirmed first LNG cargo scheduling.
Signals to Watch
First: whether FERC receives an intervention or protest before November 25 and whether it grants or conditions the sixth extension. Second: whether PHMSA approves restart of the existing pipeline following required corrective work. Third: whether Delfin supplies a more precise timetable showing completion of the onshore facilities, FLNG installation, commissioning and first commercial cargoes.
The most consequential commercial milestone will be the first export shipment backed by completed gas-delivery infrastructure and an operating liquefaction unit. Neither the investment decision nor the proposed construction deadline establishes that milestone on its own.
Delfin's newly published FERC notice confirms a sixth request for more construction time, extending the proposed onshore deadline to September 2030. Its latest DOE progress report targets first commercial LNG operations in the first half of 2031, while a separate pipeline-safety corrective-action case remains open in the latest published PHMSA data. The $5 billion first-unit investment is real, but the new deadline is still awaiting FERC approval and the remaining infrastructure and commissioning milestones are not yet complete.