SHIPUNIVERSE
Maritime Intelligence, Tools & Live Industry Radars

One place for live maritime intelligence, practical decision tools, industry events and focused reporting.

RADARS
TOOLS
All Tools
Latest 20
Open to load latest items…
NEWS
All News
Latest 20
Open to load latest items…
REPORTS
All Reports
Latest 20
Open to load latest items…
TECH
All Tech
Latest 20
Open to load latest items…
CRUISE
All Cruise
Latest 20
Open to load latest items…
NAVAL
All Naval
Latest 20
Open to load latest items…
SHIPUNIVERSE REPORTING

Reports, news and industry coverage

Full analysis in the ShipUniverse intelligence layout.

← Back to latest posts ShipUniverse / NEWS

Delfin’s $5 Billion LNG Bet Faces a Sixth Deadline Request as Filings Point to 2031 Operations

🔔 Subscribe to ShipUniverse Weekly →

Delfin LNG LLC has requested a sixth extension of the construction deadline for the onshore natural gas facilities supporting its planned floating LNG export terminal off Cameron Parish, Louisiana. The application was filed with the Federal Energy Regulatory Commission on October 30, 2026, and published in the Federal Register on November 16 under Docket CP15-490-005. Delfin is asking to move the deadline for its metering, compression and piping facilities from September 28, 2027, to September 28, 2030. The company reached a reported $5 billion final investment decision for its first floating LNG unit on June 3 and expects the vessel to arrive at the offshore port in 2030. Its separate October 1 filing with the Department of Energy projects first commercial operations in the first half of 2031. FERC has not ruled on the new extension request. Comments and interventions are due November 25, 2026.

Mapped location: Johnson Bayou and the surrounding Cameron Parish coast, the vicinity of the onshore gas infrastructure. The offshore LNG port is planned approximately 37.4 to 40.8 nautical miles from the Cameron Parish coastline. The map is a geographic reference, not a surveyed pipeline route or exact facility boundary.
2019Original FERC construction deadline
2030New onshore deadline requested
2031First-half commercial operations target
ShipUniverse | Offshore LNG Project Intelligence

The 13-Year Construction Clock Behind Delfin's $5 Billion Investment

Five approved deadline extensions, one new three-year request and several separate federal authorizations now define the path to the first commercial LNG exports.

$5BReported first-unit final investment decision
6thOnshore extension now requested
4.4MTonnes/year planned for FLNG 1
13 yrs2017 certificate to proposed 2030 deadline

How the Deadline Changed

2017Original FERC onshore facilities authorization
2019Original construction completion deadline
2023First four extensions had advanced deadline to this year
2027Current deadline following fifth approved extension
2030Sixth extension requested; NOT approved
The first four extensions were granted between 2019 and 2022. FERC granted a further four years on October 4, 2023. The pending October 30, 2026 application would add three more years.

A $5 Billion Decision Does Not Complete the Entire Gas Supply Chain

Delfin's investment decision covers its first floating LNG development phase. The facilities authorized under FERC's onshore certificate are separate infrastructure that must connect the U.S. gas network to the offshore deepwater port.

Floating LNG Development $5 billion

June 3 final investment decision, backed by investors including Global Infrastructure Partners, Mitsui O.S.K. Lines, Vitol and Diameter Capital Partners. Planned first-unit capacity is 4.4 million tonnes per year.

Samsung Heavy Industries ~$2.9 billion

Samsung's publicly disclosed construction contract for FLNG Unit 1. This is a component of the wider development, not an additional $2.9 billion to be automatically added to the $5 billion project figure.

Six Milestones That Must Not Be Confused

Construction authorizations, project investment, vessel arrival, commissioning and commercial cargo delivery represent different events.

↔ Both horizontal scrollbars are synchronized.
MilestoneDate / StatusWhat the Record EstablishesWhat It Does Not Establish
FERC Onshore CertificateSeptember 28, 2017Authorization to construct and operate specific Cameron Parish metering, compression and piping facilities.It did not authorize the offshore port or prove that onshore construction was finished.
Fifth Deadline ExtensionApproved October 4, 2023FERC granted a four-year extension, establishing September 28, 2027 as the current deadline.It did not guarantee that the work would be completed by 2027.
Offshore Deepwater Port LicenseIssued March 21, 2025MARAD authorized the offshore deepwater port under the Deepwater Port Act.It did not replace FERC's land-side construction deadlines or DOE export conditions.
First FLNG Investment DecisionJune 3, 2026Delfin announced a $5 billion FID for Unit 1 and executed construction arrangements.It is not proof that $5 billion has already been paid out or that commercial operation has begun.
Sixth FERC ExtensionSeptember 28, 2030 requestedDelfin seeks another three years for its onshore gas delivery infrastructure, citing the vessel's anticipated 2030 arrival.The extension has not yet been granted and is subject to the pending proceeding.
First FLNG Commercial OperationsFirst half of 2031, projectedDelfin's October 1 report to DOE states this expected operating window for Unit 1.This is a company projection, not proof of commissioning, first LNG production or a completed cargo.
DOE Export Commencement ConditionJune 1, 2031The current deadline for commencing authorized non-FTA exports, following DOE's 2025 decisions.The date is a regulatory condition, not a guaranteed first-delivery date.
NoteSome project milestones may occur earlier than the final regulatory deadlines. The 2030 arrival of the first offshore vessel and first-half 2031 commercial operations are separate company expectations.

Four Different Regulatory Responsibilities

FERCLand-Side Construction

Approves specified metering, compression and piping facilities and considers construction-deadline extensions.

MARADOffshore Port

Licenses the planned floating LNG deepwater port together with the Coast Guard's role in the licensing process.

DOELNG Export Authority

Maintains export authorizations and the commercial export-commencement conditions.

PHMSAPipeline Safety

Oversees applicable pipeline-safety obligations, including a separate corrective-action case concerning Delfin's existing gas pipeline.

The commercial distinction: Reaching final investment decision unlocks a major construction phase, but the physical project also depends on gas-delivery infrastructure, offshore installation, commissioning and working export arrangements. Delfin's request seeks to synchronize the onshore certificate with the timing of its first floating LNG vessel.
Important: FERC has not approved the sixth extension. The proposed 2030 date should not be described as a granted permit extension or a confirmed completion date. The $5 billion investment decision is not a verified amount already spent.
ShipUniverse | LNG Construction Risk & Federal Records

The Other Pipeline Issue Behind Delfin's 2031 Timeline

Federal safety records, a DOE progress report and an LNG buyer's securities filing expose infrastructure and commercial milestones beyond the latest FERC request.

A February Pipeline Failure Remains Part of the Infrastructure Picture

Delfin's existing offshore gas pipeline was being inspected ahead of future service when it ruptured near Johnson Bayou. The accident is documented separately from FERC's pending construction-deadline application.

February 3, 2026 56 MMcf

Approximate natural gas release reported by PHMSA, followed by a fire.

PHMSA Incident Record 1 injury

One person was injured during the pipeline failure, according to the agency.

Federal Enforcement OPEN

Corrective-action case status in PHMSA's data snapshot dated November 3, 2026.

PHMSA Corrective Action Order | CPF 4-2026-028-CAO Restart Requires Federal Authorization

The February 6 order prohibits operating the affected pipeline segment until permitted by PHMSA's regional director. Required measures include independent assessment, a root-cause investigation, repairs and an approved restart plan. The agency's early finding suggested that an inspection pig may have encountered a closed valve, but it explicitly described its investigation findings as preliminary.

Two Different Sets of Pipeline Facilities

FERC Construction-Deadline Application New Onshore Gas Facilities

Approximately two miles of metering, piping and compression facilities, including 120,000 horsepower of planned compression. The requested in-service deadline is September 28, 2030.

Separate PHMSA Corrective-Action Case Existing Offshore Gas Pipeline

An approximately 30-mile, 42-inch pipeline extending from West Cameron Block 167 toward Johnson Bayou. PHMSA says it had been out of service since 2012 before the February 2026 inspection-related rupture.

Critical reporting distinction: Both infrastructure systems are relevant to the planned offshore LNG operation, but they are not the same construction project. The new FERC extension notice cites the expected 2030 positioning of the first FLNG vessel as Delfin's reason for requesting more time. It does not identify the February pipeline rupture as the cause of the extension.

The Production Date and Commercial Delivery Date Are Different

Primary corporate, DOE and SEC filings provide a more detailed sequence than the company's investment announcement alone.

June 3, 2026 LNG Production Target | 2030 Delfin's investment-decision announcement said the first vessel was scheduled to begin LNG production during 2030.
October 1, 2026 Commercial Operations | H1 2031 Delfin's semiannual report to DOE projected first-unit commercial operations in the first half of 2031.
November 2026 SEC Filing Expand Energy Deliveries | 2031 Expand Energy's quarterly filing says its 20-year, approximately 1.15 million-tonne-per-year LNG purchase agreement anticipates commercial deliveries starting in 2031.
What the comparison shows: The latest DOE filing places first commercial operations in 2031, while the June announcement had described LNG production beginning in 2030. These are different milestones: initial production and commissioning could precede commercial deliveries. The documents alone do not establish exactly how many months of delay, if any, have occurred.

Seven Questions That Determine Whether the Schedule Holds

The following matrix separates documented obligations from the areas where construction, shipbuilding and commercial stakeholders still need specific dates or confirmations.

↔ The top and bottom horizontal scrollbars are synchronized.
Project DependencyConfirmed RecordUnresolved MilestoneWhy Shipping & Energy Stakeholders Care
Sixth FERC Extension Three additional years requested for Cameron Parish onshore metering, compression and piping facilities. FERC approval, conditions and revised construction milestone schedule. Contractors and equipment suppliers need a workable project delivery schedule; the new deadline is not yet approved.
Existing Gas Pipeline PHMSA issued a corrective-action order after the February rupture. Its enforcement database listed the case as open at the November 3 update. Verified completion of required tests, repairs and approved restart authorization. Gas-delivery readiness remains a separate requirement from constructing the floating liquefaction vessel.
FLNG Unit 1 Construction Samsung Heavy Industries announced a construction contract of approximately $2.9 billion; Delfin reached its $5 billion first-phase FID. Verified hull and topside construction progress, factory acceptance testing, delivery and offshore installation. Schedule reliability influences marine installation resources, offshore support demand and future LNG carrier availability.
Gas Supply Agreements In its October 1 DOE report, Delfin stated that it had not yet entered into long-term natural gas supply contracts. Feedgas contracting, transportation arrangements and physical commissioning supply. Long-term LNG sale agreements do not themselves prove that all required feedgas arrangements are complete.
LNG Offtake & Buyers Delfin identifies Vitol, Centrica, Gunvor and Expand among its commercial counterparties. Expand's SEC filing describes 1.15 million tonnes annually with deliveries expected in 2031. Shipment nomination windows, first commercial cargo, contractual startup conditions and final delivery arrangements. LNG carriers and buyers need actual lifting schedules before treating potential 2030 capacity as operating supply.
Export Authorization Timing DOE's current commercial non-FTA export commencement deadline is June 1, 2031. A precise startup date and confirmation that it fits the export authorization's conditions. The first-half 2031 projection spans January through June, while the existing deadline occurs June 1. That is a scheduling issue to clarify, not evidence of an existing violation.
FLNG Units 2 and 3 Delfin is separately advancing additional units and has discussed potential investment in Unit 2 with MidOcean Energy. Separate final investment decisions, construction awards, financing and commercial commissioning. Potential 13.2 million tonnes per year of total project capacity should not be counted as three operating units or three completed investment decisions.
Note A reported risk is not a confirmed delay or cost overrun. The records establish separate approval and execution milestones, but do not disclose a verified consolidated critical path or damages arising from any hypothetical missed startup date.
Next Formal Deadline November 25, 2026

Comments and motions to intervene in FERC Docket CP15-490-005 are due by 5:00 p.m. Eastern. FERC must still decide whether Delfin has shown good cause for the extension.

Next Substantive Evidence Construction & Restart Records

Look for a FERC order, pipeline restart authorization, updated Samsung delivery milestones, actual commissioning plans and confirmed first LNG cargo scheduling.

Regulatory qualification: A contested FERC extension proceeding principally addresses whether good cause exists for additional construction time. It does not automatically reopen the entire 2017 certificate or its environmental review. No approval, refusal, new pipeline operating permission or amended LNG export commencement deadline should be assumed from the November 16 notice.

Signals to Watch

First: whether FERC receives an intervention or protest before November 25 and whether it grants or conditions the sixth extension. Second: whether PHMSA approves restart of the existing pipeline following required corrective work. Third: whether Delfin supplies a more precise timetable showing completion of the onshore facilities, FLNG installation, commissioning and first commercial cargoes.

The most consequential commercial milestone will be the first export shipment backed by completed gas-delivery infrastructure and an operating liquefaction unit. Neither the investment decision nor the proposed construction deadline establishes that milestone on its own.

Delfin's newly published FERC notice confirms a sixth request for more construction time, extending the proposed onshore deadline to September 2030. Its latest DOE progress report targets first commercial LNG operations in the first half of 2031, while a separate pipeline-safety corrective-action case remains open in the latest published PHMSA data. The $5 billion first-unit investment is real, but the new deadline is still awaiting FERC approval and the remaining infrastructure and commissioning milestones are not yet complete.

Feedback Welcome

We welcome your feedback, suggestions, corrections, and ideas for enhancements.

Please click here to get in touch
By the ShipUniverse Editorial Team — About Us | Contact


← Browse more ShipUniverse posts
MARITIME DECISION TOOLS

Practical tools for real vessel and commercial decisions

Browse the latest 24 tools or instantly search every published ShipUniverse maritime tool.

24 latest toolsView all 316 →
TOOL

Offshore CO₂ Shipping Supply Chain, LCO₂ Carrier Fleet Sizing, Terminal Slots & Transport Economics Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OFFSHORE CARBON TRANSPORT…

Open →
TOOL

Shipyard Production Capacity, Critical Supplier Bottlenecks, Workforce Allocation & Newbuild Delay Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / SHIPBUILDING OPERATIONS &…

Open →
TOOL

Cruise Shore Excursion Capacity, Tour Operator Revenue Share, Cancellation Risk & Port-Day Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CRUISE & DESTINATION…

Open →
TOOL

Maritime GNSS Jamming & Spoofing, Backup Navigation Readiness, Voyage Delay & Retrofit ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / BRIDGE RESILIENCE &…

Open →
TOOL

Fleet Vessel Deployment, Ballast Positioning, Charter Opportunities & TCE Optimization Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / COMMERCIAL FLEET DECISION…

Open →
TOOL

Port Terminal Operating System Upgrade, Automation Tender, Operational Downtime & CAPEX ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / PORT SYSTEMS &…

Open →
TOOL

Floating LNG Storage Unit Investment, Bunkering Slots, Open-Access Fees & Charter ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / LNG INFRASTRUCTURE &…

Open →
TOOL

Panama Canal Transit Slot Auction, Waiting Time, Draft Restrictions & Route Diversion Economics Tool

🔔 Subscribe to ShipUniverse Weekly → ShipUniverse / Canal Access &…

Open →
TOOL

Offshore Wind O&M Vessel Fleet, CTV/SOV Scheduling, Technician Transfers & Turbine Downtime Cost Tool

🔔 Subscribe to ShipUniverse Weekly → ShipUniverse / offshore wind operations…

Open →
TOOL

Vessel Sale & Purchase Closing, Escrow, Bunker ROB, Delivery Documents & Cash Settlement Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / VESSEL TRANSACTION INTELLIGENCE…

Open →
TOOL

Harbor Tug Fleet Contract Tender, Utilization, Standby Fees & Towage Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / PORT & TOWAGE…

Open →
TOOL

Marine General Average, Cargo Contribution, Security Deposits & Claims Settlement Exposure Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / MARITIME CLAIMS &…

Open →
TOOL

Chemical Tanker Cargo Parcel Allocation, Tank Compatibility, Cleaning Turnaround & Voyage Margin Tool

🔔 Subscribe to ShipUniverse Weekly → SHIP UNIVERSE / CHEMICAL TANKER…

Open →
TOOL

Marine Insurance Claims Portfolio, Hull & P&I Loss Runs, Reserves & Renewal Negotiation Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / FLEET INSURANCE &…

Open →
TOOL

Offshore Platform Decommissioning, Vessel Spread, Weather Windows & Removal Campaign Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OFFSHORE ASSET RETIREMENT…

Open →
TOOL

Tanker & Bulker Commercial Pool, Fleet Earnings Distribution, Off-Hire & Pooling Economics Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / COMMERCIAL SHIPPING INTELLIGENCE…

Open →
TOOL

Port Terminal Concession Bid, Throughput Guarantees, Tariff Escalation & Investment NPV Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / PORT INFRASTRUCTURE INVESTMENT…

Open →
TOOL

Fleet Debt Covenant Headroom, Vessel Valuation Shock, Interest Rates & Refinancing Liquidity Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / FLEET FINANCING INTELLIGENCE…

Open →
TOOL

Maritime Freight FFA Hedging, Bunker Price Risk, Margin Calls & Cash-Flow Protection Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / FREIGHT DERIVATIVES &…

Open →
TOOL

Empty Container Repositioning, Depot Inventory, Leasing & Shortage Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CONTAINER EQUIPMENT NETWORK…

Open →
TOOL

Subsea Cable Fault Repair, Vessel Spread, Restoration Timeline & Emergency Repair Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / SUBSEA EMERGENCY RECOVERY…

Open →
TOOL

Container Shipping Service Contract, Minimum Volume Commitment, Carrier Allocation & Shortfall Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OCEAN FREIGHT PROCUREMENT…

Open →
TOOL

Fleet Retrofit CAPEX Prioritization, Fuel Savings, Decarbonization & Capital Allocation Tool

🔔 Subscribe to ShipUniverse Weekly → SHIP UNIVERSE / FLEET CAPITAL…

Open →
TOOL

Port Container Crane Fleet Replacement,Availability & Lifecycle CAPEX ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIP UNIVERSE / TERMINAL ASSET…

Open →