SHIPUNIVERSE
Maritime Intelligence, Tools & Live Industry Radars

One place for live maritime intelligence, practical decision tools, industry events and focused reporting.

RADARS
TOOLS
All Tools
Latest 20
Open to load latest items…
NEWS
All News
Latest 20
Open to load latest items…
REPORTS
All Reports
Latest 20
Open to load latest items…
TECH
All Tech
Latest 20
Open to load latest items…
CRUISE
All Cruise
Latest 20
Open to load latest items…
NAVAL
All Naval
Latest 20
Open to load latest items…
SHIPUNIVERSE REPORTING

Reports, news and industry coverage

Full analysis in the ShipUniverse intelligence layout.

← Back to latest posts ShipUniverse / NEWS

China’s ¥2 Billion Yangpu Terminal Targets LNG Tank Containers and Dangerous Cargo

🔔 Subscribe to ShipUniverse Weekly →

Yangpu Port — Hainan, China Shentou Harbor District | Lianhuashan Operating Area
Regional port reference. Exact planned terminal boundaries are not established by the published design notice.

A procurement notice published November 25, 2026, outlines additional engineering and smart-port design services for a proposed public dangerous-goods terminal at Yangpu Port's Lianhuashan operating area in Hainan, China. The project carries estimated total investment of approximately ¥2 billion, including ¥1.565 billion in construction and installation costs. Its proposed facilities include a 50,000-DWT multipurpose hazardous-cargo berth, provision for LNG tank-container vessels, 360 meters of waterfront and annual design throughput of approximately 570,000 TEU. The initial storage development is provisionally allocated 132 mu, or approximately 8.8 hectares, including dedicated LNG tank-container and dangerous-goods areas. The new design tender specifies an 80-calendar-day service period, with bids closing December 15. The notice does not establish that the facilities are operational.

Estimated Investment ¥2B Entire project estimate
Annual Design Capacity 570K TEU per year
Main Berth 50K Deadweight tonnes
Waterfront 360m Planned berth frontage
ShipUniverse | LNG & Port Infrastructure | November 26, 2026

Yangpu's ¥2 Billion Hazardous-Cargo Terminal Reveals New LNG Vessel Design and 570,000-TEU Plan

China's latest engineering solicitation details specialized containerized-gas infrastructure at Hainan's Shentou harbor district, while earlier contract awards and an existing LNG tank-container trade establish the project's wider commercial context.

Estimated Total Investment ¥2.0B

Proposed complete project investment

Construction & Installation ¥1.565B

Estimated works component

Design Throughput 570K

TEU per year; not forecast actual traffic

Initial Storage Land 8.8 ha

Approximately 132 Chinese mu

The ¥2 Billion Project Is Primarily a Construction Investment

The November 25 notice identifies a dedicated waterfront and storage development, rather than a conventional LNG receiving terminal based on large fixed cryogenic storage tanks.

OVERALL PROJECT INVESTMENT ¥2.0 billion

Estimated capital requirement for the proposed development, encompassing marine and supporting land-side infrastructure.

CONSTRUCTION & INSTALLATION ¥1.565 billion

Approximately 78.3% of the total estimated project investment.

78.3% construction and installation 100% total investment
Project ElementPublished Design BasisCommercial Interpretation
Multipurpose BerthOne 50,000-DWT rated berthMarine access for qualifying dangerous-goods and container vessels
LNG Tank-Container VesselsProvision for two 10,000-DWT vesselsSpecialized vessel-handling configuration included in the latest design description
Waterfront360 metersPlanned quay frontage
Annual ThroughputApproximately 570,000 TEUDesign capacity rather than cargo volume already secured
Initial Storage Area132 mu, approximately 8.8 hectaresProvisional first-stage land allocation
Capacity distinction: The 570,000-TEU figure applies to the proposed terminal's annual design throughput. The notice does not establish that 570,000 TEU of LNG tank containers alone will be handled, nor does it disclose an assured cargo forecast.

A Material Difference in the Published Vessel Configuration

The November design description differs from earlier 2026 EPC and supervision procurement documents.

Marine SpecificationEarlier 2026 DocumentsNovember 25 Design Notice
Primary Berth One 50,000-DWT berth One 50,000-DWT berth
Alternative LNG Vessel Arrangement One 20,000-DWT plus one 5,000-DWT LNG tank-container/container vessel Two 10,000-DWT LNG tank-container/container vessels
Waterfront Length 360 meters 360 meters
Annual Capacity Not stated in the compared procurement summary Approximately 570,000 TEU
New engineering detail: The principal berth rating and waterfront length remain consistent, but the specified LNG-vessel combination changes. That could affect berth layout and vessel-handling assumptions, although the notice does not explain whether the change has received final engineering approval.
The alternative vessel arrangements do not constitute additional independent berths. Nor does the tender establish that all described vessel combinations may operate simultaneously without restrictions. Final berthing arrangements depend on engineering design and maritime approvals.

The Storage Area Is Being Designed Around LNG Tank Containers

The new solicitation distinguishes marine facilities from supporting storage works, with the latter divided into two stages.

FIRST-STAGE STORAGE AREA 132 mu

Provisionally identified land area, equivalent to approximately 88,000 square meters.

LNG TANK-CONTAINER ZONE Dedicated Area

Planned facilities for handling and storing LNG transport tank containers.

EMERGENCY RESPONSE Dedicated Zone

Specified separation of emergency-response functions from other operational areas.

Facility ComponentPublished Scope and Design Implications
LNG Tank-Container Storage Dedicated space for LNG transport containers. Final stacking, monitoring, transfer and handling arrangements require detailed engineering.
Other Dangerous-Goods Containers Separate designated storage functions for hazardous cargoes, subject to approved compatibility and segregation provisions.
Emergency-Response Area Designated emergency facilities. The tender summary does not provide a final equipment schedule or certified emergency-response capability.
Production and Auxiliary Facilities Supporting operating buildings, utilities and associated terminal infrastructure.
Smart-Port Systems A dedicated design assignment, with individual technologies and procurement packages still to be determined.

Earlier project documents described approximately 200 mu of dangerous-goods storage land overall. The latest notice provisionally identifies 132 mu for the initial stage, rather than presenting that amount as the final footprint of both stages.

The Project Already Has a Procurement History

The November solicitation follows earlier construction and professional-services competitions for the same terminal development.

DateDevelopmentStatus
February 2025 Hainan port-planning presentation identifies a 50,000-DWT dangerous-goods berth at Lianhuashan. Official planning framework
June 2026 China Railway 20th Bureau and China Railway Fifth Survey and Design Institute consortium reported as preferred EPC bidder. Preferred-bidder reporting; not evidence of completed terminal
October 26, 2026 Construction-supervision award to Guangdong Nangang Engineering Supervision Consulting and Chengzhi Project Management. Reported award: ¥11.35 million
October 26, 2026 Cost-consulting and settlement-review award to Zhongxin International Project Management. Reported award: ¥4.169 million
November 25, 2026 Additional feasibility, engineering and smart-port design services advertised by the Fifth Survey and Design Institute. New competitive solicitation
December 15, 2026 Deadline for the latest design-services bids. Scheduled, not yet completed
Procurement distinction: The November 25 notice is not a fresh tender for the entire ¥2 billion construction program. It concerns supporting feasibility studies, preliminary and detailed design, quantity schedules and smart-port design services.
The new design contract specifies 80 calendar days of service, not 80 days to build or commission the terminal. Earlier supervision documentation provides a substantially longer design-construction and defect-liability framework.

Yangpu Has Already Moved LNG Tank Containers to Vietnam

This is the clearest evidence that the proposed facility could support an emerging logistics activity rather than a completely untested cargo segment.

JULY 7, 2026 20 LNG tank containers

Bonded LNG tank containers departed Yangpu International Container Terminal for Vietnam in a reported international transshipment operation.

PROPOSED NEW TERMINAL Dedicated facilities

The Shentou development would provide purpose-designed space for LNG tank containers and other dangerous goods, subject to completion and operating approval.

A real commercial precedent: China's National Development and Reform Commission reported the July shipment as the country's first bonded LNG tank-container international transshipment operation. It occurred at the existing Yangpu International Container Terminal, not at the proposed Lianhuashan facility.

Containerized LNG transportation can serve relatively small, distributed or intermittent demand that may not support a conventional LNG receiving terminal. The actual economics depend on container utilization, handling costs, voyage frequency, storage dwell time and onward delivery arrangements.

The Port's Wider Energy Strategy Goes Beyond LNG Containers

Yangpu's 2024–2035 port-planning framework identifies Shentou as an industrial and energy-logistics district.

Planned DevelopmentPreviously Published ScopeRelationship to New Tender
Lianhuashan Dangerous-Goods Berth One 50,000-DWT berth; earlier planning referenced 300,000 standard tank containers annually Same specialized port development; latest notice states 570,000 TEU capacity
Petrochemical Berths Six 50,000–100,000-DWT berths in the wider development plan Separate planned facilities, not included as six berths in the current design tender
LNG Loading Berths Two 50,000-DWT LNG berths, with planned capacity of 1.6 million tonnes annually Separate bulk LNG infrastructure concept
Marine Fuel Services Potential LNG, methanol and other vessel-energy services Wider port-development ambition, not a bunkering approval for this terminal
The earlier 300,000 figure refers to standard tank containers, whereas the new 570,000 figure is expressed in TEU. They should not be used to calculate a capacity-growth percentage without reconciled definitions. The separate LNG-berth plan is also not part of the single-berth project described in the November solicitation.

Where Specialized Maritime Suppliers Could Benefit

The published scope identifies categories of potential equipment and service demand, but does not constitute purchase orders for the systems below.

Supply CategoryPotential RequirementWhat Is Not Yet Established
LNG Tank Containers Transport units, inspection and maintenance services Fleet size, ownership and supplier selection
Marine Cargo Equipment Compatible quay handling, specialized lifting gear and landside transport Crane type, number and procurement value
Safety and Fire Protection Gas detection, firewater systems, emergency containment and response equipment Approved safety design and equipment specifications
Smart-Port Technology Cargo tracking, operational monitoring and terminal-management integration Software architecture, contract packages and vendors
Specialized Vessel Services LNG tank-container shipping and multimodal cargo connections Shipowners, schedules, contracts and guaranteed volumes

Four Questions Still Determine the Terminal's Commercial Value

CARGO DEMAND Contracted Volume

Whether customers will commit enough LNG tank-container and other dangerous-goods traffic to support the planned throughput.

PROJECT EXECUTION Final Design

Whether land availability, permits, marine engineering and safety approvals support the latest configuration.

INVESTMENT RETURN Operating Economics

Terminal tariffs, container handling costs, cargo mix, financing and achievable utilization have not been disclosed.

The published design solicitation does not confirm completed financing, a commissioned berth, operating licenses, guaranteed cargo, LNG bunkering authorization or a firm commercial opening date. The original notice on the China Railway procurement platform was not independently retrieved during this review.

Yangpu's ¥2 billion proposal is more advanced in procurement than the latest notice alone suggests, and its commercial rationale is strengthened by actual LNG tank-container movements already recorded through the port. The November design package adds important capacity and vessel-handling details, but the decisive tests remain engineering approval, construction delivery and enough contracted hazardous cargo to support a dedicated 570,000-TEU facility.

Feedback Welcome

We welcome your feedback, suggestions, corrections, and ideas for enhancements.

Please click here to get in touch
By the ShipUniverse Editorial Team — About Us | Contact


← Browse more ShipUniverse posts
MARITIME DECISION TOOLS

Practical tools for real vessel and commercial decisions

Browse the latest 24 tools or instantly search every published ShipUniverse maritime tool.

24 latest toolsView all 332 →
TOOL

Maritime Single Window, Port Community System Integration, Clearance Delays & Digitalization ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / PORT DIGITALIZATION &…

Open →
TOOL

Floating Drydock Capacity, Vessel Docking Slots, Yard Utilization & Investment ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / SHIPYARD CAPACITY &…

Open →
TOOL

Cruise Onboard Revenue, Beverage Packages, Casino, Specialty Dining & Guest Spending Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CRUISE COMMERCIAL INTELLIGENCE…

Open →
TOOL

Ship Sale-Leaseback, JOLCO vs Bank Financing, Balloon Payments & Equity IRR Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / MARITIME FINANCE &…

Open →
TOOL

FPSO/FSO Shuttle Tanker Fleet, Offshore Loading Windows, Storage Capacity & Production Curtailment Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OFFSHORE PRODUCTION &…

Open →
TOOL

Container Liner Service Design, Slot Charter vs Owned Ships, Empty Repositioning & Network Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CONTAINER NETWORK COMMERCIAL…

Open →
TOOL

VLCC Floating Storage vs Trading, Oil Contango, Charter Rates & Tanker Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / TANKER ASSET &…

Open →
TOOL

PCTC Vehicle Cargo Mix, Deck Capacity, Port Rotation & Voyage Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / VEHICLE CARRIER COMMERCIAL…

Open →
TOOL

Shipyard Change Orders, Scope Growth, Subcontractor Claims & Newbuild Cost Recovery Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / NEWBUILD COMMERCIAL CONTROL…

Open →
TOOL

Alternative Fuel Bunkering Network, Port Availability, Fuel Supply Contracts & Voyage Deviation Economics Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / MARINE FUEL &…

Open →
TOOL

Maritime Cloud Service Outage, Backup Communications, Fleet Downtime & Business Continuity ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / FLEET DIGITAL RESILIENCE…

Open →
TOOL

Bulk Terminal Stockpile, Conveyor & Shiploader Capacity, Vessel Queues & Demurrage Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / BULK TERMINAL COMMERCIAL…

Open →
TOOL

Offshore Cable-Laying Vessel Fleet, Installation Scheduling, Weather Downtime & Project Delay Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OFFSHORE CONSTRUCTION ECONOMICS…

Open →
TOOL

Port Electric RTG & Terminal Tractor Fleet, Charging Infrastructure, Grid Capacity & ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / TERMINAL ELECTRIFICATION INTELLIGENCE…

Open →
TOOL

Cruise Private Island Investment, Berth Capacity, Guest Spending & Destination Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CRUISE DESTINATION INVESTMENT…

Open →
TOOL

FSRU Regasification Capacity, LNG Send-Out, Gas Offtake Contracts & Conversion ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / FLOATING LNG REGASIFICATION…

Open →
TOOL

Offshore CO₂ Shipping Supply Chain, LCO₂ Carrier Fleet Sizing, Terminal Slots & Transport Economics Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / OFFSHORE CARBON TRANSPORT…

Open →
TOOL

Shipyard Production Capacity, Critical Supplier Bottlenecks, Workforce Allocation & Newbuild Delay Cost Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / SHIPBUILDING OPERATIONS &…

Open →
TOOL

Cruise Shore Excursion Capacity, Tour Operator Revenue Share, Cancellation Risk & Port-Day Profitability Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / CRUISE & DESTINATION…

Open →
TOOL

Maritime GNSS Jamming & Spoofing, Backup Navigation Readiness, Voyage Delay & Retrofit ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / BRIDGE RESILIENCE &…

Open →
TOOL

Fleet Vessel Deployment, Ballast Positioning, Charter Opportunities & TCE Optimization Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / COMMERCIAL FLEET DECISION…

Open →
TOOL

Port Terminal Operating System Upgrade, Automation Tender, Operational Downtime & CAPEX ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / PORT SYSTEMS &…

Open →
TOOL

Floating LNG Storage Unit Investment, Bunkering Slots, Open-Access Fees & Charter ROI Tool

🔔 Subscribe to ShipUniverse Weekly → SHIPUNIVERSE / LNG INFRASTRUCTURE &…

Open →
TOOL

Panama Canal Transit Slot Auction, Waiting Time, Draft Restrictions & Route Diversion Economics Tool

🔔 Subscribe to ShipUniverse Weekly → ShipUniverse / Canal Access &…

Open →