Shipbuilding Milestone, Change Order, Yard Delay & Payment Exposure Tool
Shipbuilding Milestone, Change Order, Yard Delay & Payment Exposure Tool
Connect construction work packages, owner/yard milestones, approved variations and payment evidence. Model the likely delivery date under resource constraints, trace schedule drivers and keep contractual extensions, pending change orders and financial exposure separate.
Work Packages & Predecessor Register
Unique work IDs, comma-separated predecessor IDs, planned duration, physical completion, trade and crew need. Approved change-order effort is attached to its named package; time extension is entered separately.
| Use | Work ID | Work package | Predecessor IDs | Baseline days | Complete % | Trade | Crews needed | Remove |
|---|
Yard Trade & Crew Availability
Model shared trade capacity across parallel packages. The recovery scenarios add one crew slot per trade or improve future production, without changing the contractual delivery date.
| Use | Trade code | Available crews | Work efficiency multiplier | Remove |
|---|
Variation / Change Order Register
Approved changes adjust the modeled contract price and work effort. Pending proposals are tracked separately and used only in the explicit risk scenario. A signed variation does not automatically grant an extension of time.
| Use | CO ID | Scope description | Attached work ID | Cost USD | Extra work days | Approval status | Remove |
|---|
Progress Payment & Certificate Register
Installment percentages are applied to the revised approved contract price. A payment is "earned / verified" here only when supporting evidence is verified and its work trigger is complete. Actual paid cash is reported independently.
| Use | Payment milestone | Work trigger ID | Scheduled day | Contract % | Cash paid USD | Evidence | Remove |
|---|
Yard Interruptions & Access Restrictions
Verified downtime blocks the selected trade or all active trades. Pending interruptions are monitored but not treated as certain downtime.
| Use | Cause / event | Starting project day | Duration days | Affected trade | Status | Remove |
|---|
Class, Owner & Delivery Readiness Gates
Unverified critical approvals block a "ready" status, even if the financial model shows a favorable delivery date. These are user-supplied statuses, not real-time class verification.
| Use | Evidence / gate | Category | Critical? | Status | Owner / document reference | Remove |
|---|